Project Description
This project consists of rehabilitating approximately 26,500 feet of pipeline, 30 manholes and a siphon facility in the cities of Fountain Valley, Westminster and Garden Grove. The purpose is to repair an aging pipe system and effectively serve the needs of the growing communities. Construction will extend along on Bushard Street in Fountain Valley, north of Ellis Avenue. Construction will continue west on Edinger Avenue in Westminster and move north on Magnolia Street to Westminster Blvd.
Project Status: October 2011
The Magnolia Trunk Sewer Project is now complete. We would like to thank everybody for their patience and understanding during this project. Please take a few moments to see our last project bulletin. THANK YOU!
For questions or concerns regarding this project, please contact our Construction Hotline at 714-378-2965 or email us at constructionhotline@ocsd.com
**At this time no additional OCSD projects are scheduled for the City of Fountain Valley.**