CEQA Documents for the Biosolids Master Plan

Post Date:02/14/2018 8:31 AM

For the next 45 days the public and responsible agencies will have an opportunity to review and comment on the Biosolids Master Plan Draft Programmatic Environmental Impact Report.

The proposed program includes upgrades to and construction of new biosolids handling facilities to be implemented over a 20-year planning period. The nine individual projects that would be implemented under this BMP would provide for flexible and sustainable biosolids handling to accommodate increased wastewater treatment for the future. Please click HERE to review the full Biosolids Master Plan.

A Public Meeting will be held on Thursday, March, 15, 2018 at 6 p.m. and OCSD's Plant No. 2. at 22212 Brookhurst Street Huntington Beach, California 92646.

The public review period closes on Monday, April 2, 2018. Comments can be submitted via email to CEQA@ocsd.com.