Newport Blvd District 6 Sewer Project

Newport Blvd Ramp Re-Opens

Post Date:03/08/2018

View the latest map and read on about the progress of the Newport Blvd. construction project such as the Newport ramp re-opening and the next stage of construction.  

Progress Map Mar 2018

Newport Blvd Ramp Re-Opens

By the end of this week (week of March 5), the Newport Blvd to Old Newport ramp will be completely open.  As part of the construction of the regional sewer pipeline along Newport Blvd, the ramp was temporarily closed.  Since January, only the Newport Blvd to Old Newport off ramp was accessible. 

Traffic control k-rail will be relocated to the next stage of construction, starting Thursday, March 8 at 9 p.m.  By the end of the week, the ramp will be accessible in both directions. 

There may be intermittent closures that will impact ramp access through May to finalize any finishing work such as landscaping.        

Northbound Newport Blvd Lane Closure During Construction

With the Newport Blvd ramp opening and construction project progressing, crews will be working along Newport Blvd between Hospital Rd and Industrial Way.  During work hours, the #3 northbound lane (closest to the shoulder) will be closed.  Drivers should pay attention to the traffic cones and drive cautiously through the work area. 

This next phase of work is expected to be completed in May.  No work is anticipated to occur on Newport Blvd during the summer months.

Thank you for your continued patience during the construction of this important project.

*All dates and times are subject to change based on inclement weather and other operational factors.  

_______________________________________________________________________

Follow the progress of the project and receive construction updates by signing up for e-notifications and select "Newport Blvd District 6 Sewer" in the news section.

Questions?

If you have any questions or want the most up-to-date information, please call our Construction Hotline at (714) 378-2965 or e-mail constructionhotline@ocsd.com

_______________________________________________________________________ 

Project Description:

The Newport Blvd. District 6 Trunk Sewer Relief construction project will replace an existing 60 year old regional sewer pipeline with a larger sewer pipeline to increase the sewer flow capacity and reduce the risk of spills.  Construction will take place along Newport Blvd. between Pacific Coast Highway and Industrial Way in the City of Newport Beach and Pomona Ave and 17th St in the City of Costa Mesa.  

Project Area Map 

www.ocsd.com/Newport