Sewer Construction Starting on State College Blvd.

Post Date:08/30/2018 8:07 AM

 construction alert header

Construction to replace four miles of sewer on State College Blvd. in Anaheim is starting after the Labor Day holiday. A few water lines along the project route need to be relocated to make room for the sewer, these activities will occur ahead of the sewer installation. Take a few minutes to review the upcoming activities. View the PROJECT MAP for information on additional locations.

September 2018* activities:

As early as September 4, 2018* 

Sewer Work                                                Monday – Friday, 7 a.m. – 7 p.m.

Cerritos Avenue to Ball Road**

• One northbound and one southbound lane closed (one additional lane may be closed between 8:30 a.m. – 3:30 p.m.) 
• Winston at State College will be closed to install sewer across the intersection, additional details will be provided as we approach the area.

Mid-September 2018* 

Water line relocations                              Monday – Friday, 8:30 a.m. to 3:30 p.m.

 State College Blvd. and Winston Avenue (work will be done in two phases and occur sequentially)

Phase 1: 
o State College northbound travel lanes reduced at Winston 
o South and east cross walks closed 
o Northbound bus stop closed at State College just south of Winston 
o No parking on Winston (near the intersection of State College only) 

• Phase 2: 
o Left turn from State College heading west to Winston will be closed 
o South cross walk closed 
o No parking on Winston (near the intersection of State College only)

 State College Blvd. and Ball Road (work will be done in two phases and occur sequentially)

Phase 1: 
  o State College southbound travel lanes reduced at Ball Road 
  o Eastbound travel lanes on Ball Road reduced at State College 
  o West cross walk closed 
  o No left turns from Ball Road heading north on State College 

• Phase 2: 
   o All left turns restricted 
   o Lane reductions in every direction

**Due to the nature of the work, major intersections will take place at different times, details to follow as construction progresses. 
  

We understand construction can be an inconvenience, we apologize in advance and appreciate your patience as we work to improve our infrastructure.

Please look at the menu for additional project details and contact information.


*Dates are subject to change due to operational factors or inclement weather.

______________________________________________________________________

Project Description: 
The project is replacing four miles of sewer along State College Boulevard from the SR-91 to Orangewood Avenue in the City of Anaheim. Construction is scheduled to begin in summer 2018 and conclude in late 2020.  Once the project is complete, nine million gallons of wastewater will be diverted to OCSD’s Plant No. in Fountain Valley for treatment before being send to the Groundwater Replenishment System.  This is Phase B of a two-phase project; Phase A was completed in 2017 and took place from Yorba Linda Blvd. to SR-91 in the City of Fullerton.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer