Wrapping things up on the Newhope Project

Post Date:08/25/2017 2:57 PM

Crews working on the Newhope Project on State College Blvd. in Fullerton and a section of Anaheim are wrapping things up. Now that the pipe is fully installed and construction is complete, crews are focusing on the very last few items to officially complete the project.

Over the next few weeks you’ll see crews making the final adjustments to several manholes and completing any pending repairs.  These activities will require minimal traffic control and will take no more than a few hours at each location.  

After the Labor Day weekend landscaping work will begin at the two medians north and south of the 91 freeway. The work will be isolated to the medians; a traffic lane may be impacted sporadically as material is delivered.  Landscaping should be completed by the end of September.

median

(median south of SR-91 to be landscaped)

We truly appreciate the understating and patience the community has shown during this very important sewer line project. This project successfully installed over two miles of sewer which will allow us to reclaim more water and abandon a pump station in Fullerton.

Next year construction of Phase B of the project will commence. Phase B extends on State College Blvd. from south of the 91 freeway to Orangewood Avenue in the City of Anaheim.

Questions?

If you have any questions or want the most up-to-date information, please contact our designated community liaison at the Construction Hotline at (657) 208-7900 or e-mail us constructionhotline@ocsd.com

______________________________________________________________________

Project Description:

This project is replacing a sewer line along State College Boulevard from Yorba Linda Boulevard to Orangewood Avenue in the cities of Anaheim and Fullerton. The project is divided in two phases: A and B. Phase A started construction in May 2016 and will be completed in summer 2017. Phase B construction is tentatively scheduled to begin in mid-2018. 

 www.ocsd.com/newhope

 